Question

When is a building permit not required?

Answer See handout BPC-005
Question The building inspector asked me for a CF-6R form and a IC-1 form. Where can I get them? What are they?
Answer

These forms are required by the California Energy Commission (CEC) and are available on the CEC website. Both forms must be posted at the building site. A copy of each must also be given to the building inspector at the final inspection.

 

The CF-6R form is an installation certificate that is completed by contractors who install plumbing, mechanical and fenestration products and systems.

 

The IC-1 form is an insulation certificate that is completed by contractors who install building insulation.

Question

Can I receive a refund of my building plan check or building permit fees if I cancel or withdraw the project?

Answer Refunds are regulated by the California Building Code (CBC) which reads:

"Under Section 107.6, CBC, the building official may authorize refunding of not more than 80 percent of the plan review fee paid when an application is withdrawn or canceled before any plan reviewing is done. The building official may authorize refunding of not more than 80 percent of the permit fee paid when no work has been done under the permit.

There shall be no refunding of any fee paid except on written application filed by the original permittee not later than 180 days after the date of fee payment."

Question

I've applied for a building permit, submitted my plans and paid my plan check fees. Will I have to pay any additional fees?

Answer

Yes. When your plans have been checked for compliance with all appropriate building codes and regulations, additional fees will be due, depending on the type and scope of the project.
You must also obtain all necessary clearances before your permit can be issued. All clearances needed should be identified on the "Building Permit Application Checklist" that was given to you when you submitted your application.

Question

My building permit has been issued. I was given the permit, a job card and a set of plans. What do I do now?

Answer

You can now begin construction. Your approved plans, job card and any other documents your received must be posted on the job site in an easily visible location. The job card will be used by the inspector to record progress on the required inspections. The set of plans will be used to verify that all construction is in compliance with the approved plans. The job card and plans must be kept on-site and available for the inspector's use.

Question I've been told my project requires a site review. When will this occur?
Answer

The site review inspector will visit your site within 5 to 10 working days of the receipt of your plans and payment for the site review fee. Plans must meet PRMD requirements. The site address must be posted at the road and be clearly visible from both directions. The corners of the proposed building site must be marked with stakes before inspection can occur.

Question

Will I receive a phone call from the site review or building inspector before my inspection?

Answer The inspector will not contact you prior to your inspection.
Question

How does the building inspector know when to come to my project for the required inspections?

Answer

Inspections, other than site review, are scheduled over the phone usingAcrobat Document Selectron - an automated inspection request system. You will be given instructions for using this system when your permit is issued. The phone number is (707) 565-3551. You must call before midnight to schedule an inspection for the next work day.

Question

I've scheduled an inspection through Selectron. What time will the inspector come to my project?

Answer

Inspections are set for early morning, mid-day or afternoon. To check on the inspector's estimated arrival time you can call on the day of the inspection as specified:
8 to 10 a.m. — 565-1679
10 to 12 p.m. & 1 to 5 p.m. — 565-1900

Note: No PRMD phone operator between 12 to 1 pm DAILY


You will need to tell us the address and permit number of the project when you call. We can provide faster service if you also give us the inspection area number that is located in the lower right corner of the front of your permit.

Question

The entrance to my property is secured by a gate with a coded lock. How will I get this information to the inspector?

Answer You can;
 

Write the code on the original building permit application before it is issued or give the code to the cashier at the time the permit is issued.

After the permit has been issued, call (707) 565-1900 during regular phone hours. Give the telephone operator the address of your project and they will transfer you to your inspector's voicemail. Leave the code on the inspector's voice mail.

Question How long is my building permit valid?
Answer

Building permits issued on or after July 1st, 1999 are valid for 3 years from the date of issuance and can not be extended. Building permits issued before this date are valid for 180 days. An inspection extends the permit life for an additional 180 days. If a permit expires, a new permit and applicable fees will be required. A plan check may also be required.

  PRMD Home | About PRMD | Boards & Commissions | Forms & Applications | Online Permits | Fees | Permit History | Permit Reports | Zoning | Policies & Procedures | Historic Resources | Storm Water | FAQ's | Links
Although every effort is made to provide complete and accurate information on this website, users are advised to contact appropriate PRMD staff before making project decisions. This may involve contacting more than one section within PRMD (e.g. Building, Plan Check, Zoning, Well & Septic, etc.), since each section implements specific codes or ordinances which may affect your project.
Sonoma County Home | Site Index | Contact Us | Search | Accessibility | This page was last updated by webmaster
Permit and Resource Management Department County of Sonoma